Application upgrade

note

This document describes how to upgrade your application. If you are looking specifically for the changes to perform between SDK versions, see the SDK migrations documentation.

danger

This section is currently incomplete. Track the progress of this document here.

Pre-Upgrade Handling

Cosmovisor supports custom pre-upgrade handling. Use pre-upgrade handling when you need to implement application config changes that are required in the newer version before you perform the upgrade.

Using Cosmovisor pre-upgrade handling is optional. If pre-upgrade handling is not implemented, the upgrade continues.

For example, make the required new-version changes to app.toml settings during the pre-upgrade handling. The pre-upgrade handling process means that the file does not have to be manually updated after the upgrade.

Before the application binary is upgraded, Cosmovisor calls a pre-upgrade command that can be implemented by the application.

The pre-upgrade command does not take in any command-line arguments and is expected to terminate with the following exit codes:

Exit status codeHow it is handled in Cosmosvisor
0Assumes pre-upgrade command executed successfully and continues the upgrade.
1Default exit code when pre-upgrade command has not been implemented.
30pre-upgrade command was executed but failed. This fails the entire upgrade.
31pre-upgrade command was executed but failed. But the command is retried until exit code 1 or 30 are returned.

Sample

Here is a sample structure of the pre-upgrade command:

func preUpgradeCommand() *cobra.Command {
cmd := &cobra.Command{
Use: "pre-upgrade",
Short: "Pre-upgrade command",
Long: "Pre-upgrade command to implement custom pre-upgrade handling",
Run: func(cmd *cobra.Command, args []string) {

err := HandlePreUpgrade()

if err != nil {
os.Exit(30)
}

os.Exit(0)

},
}

return cmd
}

Ensure that the pre-upgrade command has been registered in the application:

rootCmd.AddCommand(
// ..